Utilize este identificador para referenciar este registo: http://hdl.handle.net/11144/5070
Título: A real options model to determine the optimal contractual penalty for a BOT project
Autor: Ribeiro, João A.
Pereira, Paulo J.
Brandão, Elísio M.
Palavras-chave: Real options
Option to defer
Public-private partnerships
Social costs
Optimal contractual penalty.
Data: 2021
Editora: CICEE. Universidade Autónoma de Lisboa
Resumo: Public-Private Partnerships (PPP) became one of the most common types of public procurement arrangements and Build-Own-Transfer (BOT) projects, awarded through adequate bidding competitions, have been increasingly promoted by governments. The theoretical model herein proposed is based on a contractual framework where the government grants leeway to the private entity regarding the timing for project implementation. However, the government is aware that delaying the beginning of operations will lead to the emergence of social costs, i.e., the costs that result from the corresponding loss of social welfare. This fact should motivate the government to include a contractual penalty in case the private firm does not implement the project immediately. The government also recognizes that the private entity is more efficient in constructing the project facility and also in running the subsequent operations. The model’s outcome is the optimal value for the legal penalty the government should include in the contract form. Sensitivity analysis reveals that there is a level for each of the comparative efficiency factors above which there is no need to impose a contractual penalty, for a given level of social costs. Finally, the effects of including a non-optimal penalty value in the contract form, which derives from overestimating or underestimating the selected bidder’s real comparative efficiency are examined, using a numerical example. Results demonstrate that overestimating (underestimating) the selected bidder’s real comparative efficiency leads to the inclusion of a below-optimal (above-optimal) value for the legal penalty in the contract and produces effects the government should prevent by estimating the comparative efficiency factors with full accurac.
Revisão por Pares: no
URI: http://hdl.handle.net/11144/5070
metadata.dc.identifier.doi: https://doi.org/10.26619/UAL-CICEE/WP06.2021
Aparece nas colecções:WPs_2021

Ficheiros deste registo:
Ficheiro Descrição TamanhoFormato 
A_Real_Options_Model_to_Determine_the_OCP_for_a_BOT_Project (2).pdf208,05 kBAdobe PDFThumbnail
Ver/Abrir


FacebookTwitterDeliciousLinkedInDiggGoogle BookmarksMySpaceOrkut
Formato BibTex mendeley Endnote Logotipo do DeGóis Logotipo do Orcid 

Todos os registos no repositório estão protegidos por leis de copyright, com todos os direitos reservados.